Just-in-time approach for component delivery on green power plant

Fourth Quarter 2025 Electrical switching & drive systems & components

Space is often the primary consideration when undertaking construction work at power plants. Modular construction techniques, along with the precise coordination and delivery of components to site, are the most effective methods to ensure power plant projects proceed smoothly. Mammoet was approached to assist EnBW in constructing a new power plant in Altbach/Deizisau, Germany. The new combined cycle gas turbine fuel-switch power plant will serve as a green energy facility, capable of operating on natural gas, hydrogen, or blends of the two, instead of coal.

Constructing a new power plant adjacent to an existing one posed a significant challenge, with maximising space and minimising disruption being the foremost priorities. To address these challenges, a just-in-time approach was implemented, which significantly alleviated congestion at the site during the construction process. Additionally, the construction of a temporary jetty enabled the main crawler crane to operate continuously, facilitating the offloading of the components and their subsequent installation.

Getting the heavy items to site, just in time

The initial challenge was determining how to transport the heavy items to the construction site and where to store them. Although a storage area was available on site, it was insufficient to accommodate the needs of this project. Faced with a large list of components to deliver and insufficient space to store them, Mammoet temporarily stored the largest items at its storage yard in Schiedam, the Netherlands. Transported to Schiedam by sea, the components were subsequently marshalled, stored, scheduled for delivery, and shipped to Altbach just-in-time on specialised river-going vessels. The river Neckar runs alongside the power plant, which has an existing jetty. However, utilising this jetty as a trans-shipment point was not feasible as it would have significantly interfered with the activities at the site.

Many complex components, very little space

Numerous components required storage and subsequent shipment to the site, including HRSG modules, a generator, a gas turbine, a transformer and stack modules. The 15 HRSG modules, weighing between 80 and 250 tons, presented a particular challenge due to their 30 metre length, which rendered them exceptionally fragile.

“It is a flexible module that does not tolerate deformation and therefore had to be kept perfectly straight at all times,” explains Leonid Sinelnikov, project manager at Mammoet. “We meticulously examined every stage of their handling to ensure they remained undamaged. This included ground preparation at Schiedam and the use of specialised lifting beams and rigging tools for their transportation and offloading.”

Two crawler cranes, a main 1350 ton crane and a 600 ton tailing crane, were utilised to tail up the HRSG modules from a horizontal to a vertical position. Additionally, the modules had to be lifted over the top of a building. Due to the extended length of the crane’s boom, clearance was required from Stuttgart Airport to execute the lift.

The installation of the 400 MW gas turbine presented another complex challenge. A late requirement specified that its base plate had to be perfectly level due to the construction of its supports. “This is not standard practice for a cargo exceeding 350 ton,” notes Sinelnikov. “Heavy steel rigging typically allows for some tolerances. Massive slings and grommets are never exactly the same length, which would not meet the precise tolerances required by the client.”

To address this, strand jacks were integrated into the crane’s rigging, enabling the team to level the unit during the lift prior to installation. The six stack modules, which combine to form a large chimney, were among the most logistically challenging components to deliver, as they had to be transported via a public road.

These sections were prefabricated offsite and transported using two 12-axle lines of Mammoet self-propelled modular transporters. The team identified the optimal route to minimise site modifications, conducting a 3D scan of the path from the fabrication site to the final installation location.

The modules, measuring up to 18 metres in height and weighing 95 tons, had to be elevated onto a support structure to provide sufficient clearance and reduce on-site preparations. Although the units needed to traverse just 75 metres of public road, a journey that could be completed in minutes, the preparation and planning required several weeks.

A genuine team effort

With numerous complex components needing to be delivered to an active site where multiple contractors were working simultaneously, success rested on meticulous planning, careful execution and clear communication. From the sales and planning teams to the engineers and the project team managing operations on the ground, it was a genuine team effort to deliver this comprehensive end-to-end solution.

For more information contact Jana Wolf, Mammoet, [email protected], www.mammoet.com




Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Axial piston pump series for next-gen hydraulic applications
Electrical switching & drive systems & components
Moog has launched its new AXP Axial Piston Pump Series, a next-generation hydraulic solution engineered to deliver optimal performance, reliability and cost efficiency for industrial applications.

Read more...
Strain wave gearheads for precision and compact design
DNH Technologies Electrical switching & drive systems & components
Strain wave gearheads from maxon are a specialised type of gearhead where precision and compact design are crucial.

Read more...
World’s hottest engine
Editor's Choice Electrical switching & drive systems & components
Scientists have built the world’s smallest engine. It’s also the world’s hottest. It could provide an unparalleled understanding of the laws of thermodynamics on a small scale, and provide the foundation for a new, efficient way to compute how proteins fold.

Read more...
Next-gen planetary gearboxes
SEW-EURODRIVE Electrical switching & drive systems & components
Leading the way in planetary gear unit innovation, SEW-EURODRIVE is extending its reach across a growing range of industries, delivering the advantages of this powerful technology through locally engineered solutions that ensure faster lead times.

Read more...
Beckhoff’s XPlanar boosts productivity in medical device assembly
Beckhoff Automation Electrical switching & drive systems & components
The intelligent transport system, XPlanar from Beckhoff provided the basis for an innovative system concept allowing the specialists at Automation NTH to reduce the space requirement of an assembly machine for medical diagnostic devices by a factor of 10.

Read more...
Smart features increase crane safety
Electrical switching & drive systems & components
The newly launched Konecranes S series hoist offers a large bouquet of smart features which not only increase lifting device safety but also deliver a higher level of operator protection.

Read more...
Redefining industrial lifting
Electrical switching & drive systems & components
The Konecranes S-series hoist redefines industrial lifting through its integration of a ground-breaking synthetic rope with smart features, a lifting capacity of 20 tons, and the ability to adapt to diverse girder configurations.

Read more...
Seven years of uninterrupted service
Electrical switching & drive systems & components
A set of hydraulically operated Corflex pinch valves, installed in 2018 at a major North African gold mine, has delivered in one of the continent’s most demanding slurry-handling applications.

Read more...
New generation soft starter ranges
Schneider Electric South Africa Electrical switching & drive systems & components
Schneider Electric has launched its new generation Altivar ATS430 and ATS490 soft starter ranges in Anglophone Africa, the latest innovations in motor control technology.

Read more...
Reinventing the wheel
Editor's Choice Electrical switching & drive systems & components
Once a curiosity in the early automotive age, in-wheel motors are now re-emerging with real promise. From electric cars to commercial vehicles and even aircraft, they are on the verge of transforming transportation engineering.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved