Electrical switching & drive systems & components


Rapid headframe replacement for Canada’s biggest potash mine

Second Quarter 2026 Electrical switching & drive systems & components

Potash, a fine-grained mineral that contains potassium and is commonly used in food production, is in abundance in Saskatchewan, Canada. Mammoet has supported Ledcor with the construction of BHP’s new Jansen potash mine which is planned to begin production in 2027. It will become one of the largest potash mines in the world and is estimated to produce approximately 8,5 million tons per annum when it is fully operational.

A mine’s headframe is positioned above the shaft, delivering people, equipment and materials below and above ground. The key scope for Mammoet was to remove the lower section of an existing headframe unit and replace it with a larger one to increase mining capacity.

Separately, it also supported with the complex lifting of a staircase tower module from inside the building where it was to be installed.

With Jansen’s remote location, modular construction techniques enabled the units to be prefabricated, delivered, assembled on site and installed efficiently. This approach, enabled by Mammoet’s heavy lifting and transport expertise, limited the amount of construction equipment and operators on site, and allowed parts of both components to be built in parallel, shortening the project schedule relative to other methods.

Planning collaboratively

The project had been in planning for many years. Mammoet’s introduction to it first started in 2013, when the original headframe unit was built. The modules for the new headframe were prefabricated at specialist facilities in the city of Edmonton and other places in the province of Alberta. The modules for the staircase tower were also built in Edmonton.

The parts were transported to the site on platform trailers fitted with transport beams. This phase wasn’t without its challenges, as Mike de Wilde, project manager at Mammoet, explains: “Jansen is mainly farmland, so you will often see agricultural equipment and machinery being transported on its roads, but shipping these large modules presented issues when staging our trucks overnight. We couldn’t just pull into a normal layby because the trucks would fill the entire area. The schedule had to be carefully planned and managed”.

During this planning phase, the ground condition on site was also an important consideration. During the spring the ground becomes soft and wet, so the team performed a ground-loading test between the laydown area and the mine shaft.

SPMTs carrying counterweights tested the route so that areas of potential sinking could be identified. As a result, more than 400 crane mats were mobilised because the ground was deemed too soft.

A section of ground by the shaft opening also needed to be reinforced to take the weight of the new headframe module. A shoring system, constructed of 21 metre towers was constructed at a basement level to provide stability. Due to the size of Mammoet’s global fleet, extra steel supports could be mobilised from its Dubai and United Kingdom yards, reducing overall risk levels despite the tough conditions.

The real heavy lifting begins

With the modules on site, the team began removing the existing headframe and prepared for the installation of the new one. A 22 axle line and 20 axle line SPMT combination, both fitted with steel supports, were driven underneath the 796 ton headframe module. The supports were necessary as using crane mats would have exceeded the ground-bearing pressure limits.

The SPMTs lifted the headframe using their onboard stroke, allowing Ledcor and BHP teams to remove the temporary steel supports, then the unit was driven to a laydown area.

Before the new headframe could be installed, Mammoet supported with the connection of a 60 ton staircase tower inside it.

An LR1300 crawler crane lifted in strand jacks and other equipment through an opening at the top of the building. The team then assembled the intricate winch system to lift the staircase tower.

The system comprised strand jacks and also spools to secure the 65 metres of cable needed to pull the staircase tower module from the bottom to the top of the building.

The removal of the original headframe unit left a large opening at the base of the building, enough space to manoeuvre the staircase module in range of the strand jacks using and LR1500 crawler crane. Once the unit was inside the building, its position was manually adjusted using pullies and chain hoists so it could be secured and lifted.

Adapting to challenges

The last phase of the project was the installation of the new headframe, which weighed 2090 tons, an almost 1300 ton increase from the previous headframe.

A configuration of two double SPMT trains, with a combined 80 axle lines were used for the movement. Finding the best configuration proved the biggest challenge.

“We had to find a trailer configuration where we could carry the additional weight, be under the permissible ground-bearing pressure, plus be short enough to not clash with the existing structure,” explains de Wilde. “Making this installation even more difficult was the fact that a section of the new headframe had to dock inside the staircase tower building. We were pretty much stroked out with the SPMTs, so it was a very tight fit. We had to align the head frame precisely with bolt positions specified in the engineering plans. Ledcor arranged for guidance lasers to be set up at the end of the platform and our SPMTs had to align with them perfectly, because every deviation could cause serious problems when it came to setting the module down. It was a very precise manoeuvre.”

This project demonstrates Mammoet’s skill when it comes to modular construction and efficient fabrication-to-foundation solutions. The option to use fabrication facilities and deliver everything to the site was a huge benefit in terms of schedule and cost efficiency.

A lot of specialised engineering went into making sure that everything arrived on schedule and was connected smoothly. This is where Mammoet excels, meeting the demands of its customers and delivering excellence in engineering, delivery and safety.

For more information contact Mammoet Global, +31 622 63 5062, [email protected], www.mammoet.com




Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Supporting construction of next-gen floating offshore wind turbines
Electrical switching & drive systems & components
While windy locations naturally make ideal spots for offshore wind farms, they bring challenges when it comes to assembling wind turbines, particularly in ports. Mammoet was approached by Euroports to support with the marshalling and assembly of the components that make up the three turbines at Port-la-Nouvelle in France.

Read more...
Topside decommissioning projects streamlined with combined planning
Electrical switching & drive systems & components
Mammoet has been working with Allseas for many years, supporting it to offload some of the world’s biggest topsides from its specialist vessels onto quaysides for disposal.

Read more...
Unlocking easier automation
Electrical switching & drive systems & components
As automation systems grow more complex, machine builders are rethinking how they design and deploy motion. A new generation of servo technology is helping manufacturers simplify design, improve flexibility and build greater resilience into their supply chains.

Read more...
The mechatronic approach to designing motion as a system
Electrical switching & drive systems & components
Mechatronics is something engineers have been working toward for decades, designing machines where the mechanical, electrical and control systems work together as one. What’s changed is the level of sophistication we can now achieve, and the expectation that we should.

Read more...
Condition monitoring for hydroelectric plants
ifm - South Africa Electrical switching & drive systems & components
The energy company Compagnia Valdostana delle Acque generates electricity in the region’s 32 hydroelectric power plants with a total capacity of over 900 MW. Vibration sensors from ifm monitor the maintenance requirements of the turbines and power generators at all times.

Read more...
When restoring worn pumps makes cents
Electrical switching & drive systems & components
Through its extensive SupremeServ operation, pump manufacturer KSB Pumps and Valves is able to repair a wide range of pumps and valves to original OEM specification at a significantly lower cost than new equipment.

Read more...
How to size and select a servo motor
Festo South Africa Electrical switching & drive systems & components
Festo highlights some factors to consider in the process of sizing and selecting a servo motor effectively to ensure optimal performance, reliability and energy efficiency.

Read more...
Internationally engineered valves support uptime in tough conditions
Bearing Man Group T/A BMG Electrical switching & drive systems & components
BMG’s Fluid Technology division works closely with industry in sub-Saharan Africa to ensure that all valves, strainers and flow control equipment supplied meet the exact requirements of every application and also conform with stringent industry standards.

Read more...
Solving common automation challenges with Festo’s servo drive and servo motor solutions
Festo Editor's Choice Electrical switching & drive systems & components
Automation projects face challenges that include limited installation space, the need for precise and repeatable linear motion, rising cycle-speed demands, and seamless integration with existing control architectures. Festo’s servo portfolio directly addresses these issues with compact, modular drive and motor solutions designed for specific applications.

Read more...
Inside the Giant Magellan Telescope with mechanical engineering at astronomical scale
Editor's Choice Electrical switching & drive systems & components
Construction of the Giant Magellan Telescope, set to become the world’s largest Gregorian optical infrared telescope, is well underway. While its scientific mission is to transform astronomy, its performance depends heavily on advanced mechanical, hydraulic and pneumatic engineering.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved